// HAM · Completed
RKC – ARCPL Rudrapur Highway Pvt. Ltd.
A 43.4 km road asset held under the Hybrid Annuity Model, commercially operational since March 2024.
- Location
- Rudrapur, Maharashtra
- Contract value
- ₹350 crore financial asset
- Length / span
- 43.446 km
- Scope
- Road asset under the Hybrid Annuity Model
- Delivery model
- HAM
- Status
- Completed
- Completion
- COD March 2024
43.4 km Highway asset
₹350 cr Financial asset
HAM Delivery model
Mar 2024 Commercial operation
[01] About the project
The Rudrapur highway is one of RKC's road assets under the Hybrid Annuity Model: a 43.446 km highway that RKC built and now operates and maintains through the concession period.

The asset reached its commercial operation date in March 2024 and represents a financial asset of ₹350 crore.
Scope of work
- Construction of the 43.446 km highway
- Pavement, drainage and structures
- Road safety works, signage and markings
- Operation and maintenance through the concession period
Owning the outcome
With HAM, the contractor finances part of the build and is paid back through annuities over the years that follow. That ties RKC to the road for the long term: its quality on handover, and its condition years later, are both RKC's responsibility.